GRAVITY GOODS ROPEWAY
8.3 Site Instruction Book
During construction, a site instruction book must be kept on site to record those instructions
issued by the supervisor, engineer and suggestions given by other inspectors visiting the site.
8.4 Site Diary
The site supervisor should keep a site diary in which notes of daily operations are documented. The diary
will also include the records of visitors to the site, decisions made at the site and any occurrences like
rainfall, climatic conditions, labour shortfall, and delay in material transport which are likely to affect
the administration of the project.
42